• Skip to main content
  • Skip to search
  • Skip to footer
Cadence Home
  • This search text may be transcribed, used, stored, or accessed by our third-party service providers per our Cookie Policy and Privacy Policy.

  1. Community Forums
  2. PCB Design
  3. net assignment question

Stats

  • Locked Locked
  • Replies 5
  • Subscribers 166
  • Views 14282
  • Members are here 0
More Content
This discussion has been locked.
You can no longer post new replies to this discussion. If you have a question you can start a new discussion

net assignment question

masamasa
masamasa over 6 years ago

hello

how can i assign a net as a ground or power?

based on the artical below, i should identify the power and ground nets in order to maximize the performance but i do not know how.

https://community.cadence.com/cadence_blogs_8/b/pkg/posts/how-to-maximize-performance-when-your-package-layout-gets-complicated

i assume i need to assign some nets as ground or power in the constraint manager.

currently all nets on the netlist are assigned as a signal net so any command takes a long time to execute.

  • Cancel
  • steve
    steve over 6 years ago

    In Constraint Manager go to Properties - Net Properties - General and add a Voltage value for the Power and GND nets. They will then display differently in the design (so not point to point but show a square with a cross in the middle on each pin). 

    • Cancel
    • Vote Up 0 Vote Down
    • Cancel
  • masamasa
    masamasa over 6 years ago in reply to steve

    thank you steve

    i was able to set up the ground and power nets and saw a cross in the middle on each pin.

    but i do not see any significant performance difference on each command yet.

    you always help me a lot.

    anyway thank you again.

    • Cancel
    • Vote Up 0 Vote Down
    • Cancel
  • masamasa
    masamasa over 6 years ago in reply to masamasa

    one more question,

    i got this message after i run the performance advisor on dbdoctor.

    * PLANE_FL3 net has VOLTAGE property, but the ratsnest schedule is is NOT  "POWER_AND_GROUND".

    how can i set the nets with the voltage property i specified as "power and ground" on the ratsnest schedule?

     

    • Cancel
    • Vote Up 0 Vote Down
    • Cancel
  • steve
    steve over 6 years ago in reply to masamasa

    Try Edit - Properties on the net (Find pane) then choose Ratsnest_Schedule and set Power and Ground. Not convinced this will give you a huge saving either.

    • Cancel
    • Vote Up 0 Vote Down
    • Cancel
  • masamasa
    masamasa over 6 years ago in reply to steve

    thank you steve

    i was able to setup the ratsnest schedule.

    • Cancel
    • Vote Up 0 Vote Down
    • Cancel
Cadence Guidelines

Community Guidelines

The Cadence Design Communities support Cadence users and technologists interacting to exchange ideas, news, technical information, and best practices to solve problems and get the most from Cadence technology. The community is open to everyone, and to provide the most value, we require participants to follow our Community Guidelines that facilitate a quality exchange of ideas and information. By accessing, contributing, using or downloading any materials from the site, you agree to be bound by the full Community Guidelines.

© 2025 Cadence Design Systems, Inc. All Rights Reserved.

  • Terms of Use
  • Privacy
  • Cookie Policy
  • US Trademarks
  • Do Not Sell or Share My Personal Information